作者:Joey Espinoza @joey
I have selected 4 package tags with various plant counts. I want to create plant batches from those four. When I tried this TTT ended up creating only from one package (1 of the 4 I selected) and it caused that package tag to go into negative numbers. Is there a way for TTT to not allow this by knowing it will be negative? In METRC before you make it negative it will have a confirmation checkbox you must click

- M回复joey⬆:Matt Frisbie @mattfriz
After looking through everything, I'm adding some extra safeguards to the package split calculation to ensure this doesn't happen. Fix going out later today.
I'm closing this issue for now, feel free to reopen if the issue isn't addressed.
- 进展与解决此问题有关